Boston University Myles Standish Hall Renovations

Kenmore Square, Boston, MA


Type of Project: Fit-Out
Duration of Project: 27 months
Square footage: 204,275 sf
Partners: Design/Build Partner: MDS|Miller Dyer Spears, OPM: Compass Project Management

Noteworthy: Design/build complete renovation of 204,275 sf historic (1925) dormitory located at the corner of Bay State Road and Beacon Street in Boston’s Kenmore Square. The main building (9-story structure plus basement) and 4-story annex were divided into three distinct construction zones. While one zone was isolated for renovation, the other two were fully occupied by students during the academic year.

Awards: IFMA Boston 2019 Best Practices: Large Project Award / 2019 Preservation Massachusetts Paul & Niki Tsongas Award / DBIA New England Region 2018 Silver Award for Building Construction